On Now
Coming Up
  • Tue., May. 21, 2013 11:30AM - 1:00PM CDT Organized Team Activities (OTAs) The Packers announced details on the remainder of their offseason schedule, including the fact that five of the team’s offseason practices will be open to the public, weather permitting.

    The open practices will be three organized team activities (OTAs) and two mandatory minicamp workouts. The open OTA practices are slated for three Tuesdays — May 21, May 28 and June 11 — and will begin at 11:30 a.m. CT. The two mandatory minicamp practices are scheduled for June 4 and 5 with a start time TBA.

    Due to ongoing preparations on Ray Nitschke Field for training camp, the OTA and minicamp workouts will be held on Clarke Hinkle Field this year. Viewing of the open practices will be standing-room only along the Oneida Street side of Hinkle Field.

  • Tue., May. 28, 2013 11:30AM - 1:00PM CDT Organized Team Activities (OTAs) The Packers announced details on the remainder of their offseason schedule, including the fact that five of the team’s offseason practices will be open to the public, weather permitting.

    The open practices will be three organized team activities (OTAs) and two mandatory minicamp workouts. The open OTA practices are slated for three Tuesdays — May 21, May 28 and June 11 — and will begin at 11:30 a.m. CT. The two mandatory minicamp practices are scheduled for June 4 and 5 with a start time TBA.

    Due to ongoing preparations on Ray Nitschke Field for training camp, the OTA and minicamp workouts will be held on Clarke Hinkle Field this year. Viewing of the open practices will be standing-room only along the Oneida Street side of Hinkle Field.

  • Sat., Jun. 01, 2013 8:30AM - 3:30PM CDT Junior Power Pack Clinic The 16th Annual Junior Power Pack Clinic will take place June 1, 2013 inside the Don Hutson Center, the Packers indoor practice facility. Reserved exclusively for members of the Junior Power Pack kids fan club (ages 5-14), this event features the chance to run skills and drills with other Packer backers and a few up-and-coming Packers players.
  • Sat., Jun. 08, 2013 3:00PM - 5:00PM CDT Jerry Parins Cruise for Cancer The Green Bay Packers are gearing up for the 10th annual Jerry Parins Cruise for Cancer event, set for Saturday, June 8. The event once again features a motorcycle ride, but non-riding fans who want to support the cause are welcome to attend the post-ride party at Lambeau Field’s North Loft, the rooftop deck below the TundraVision in the north end zone.
     
    On the day of the ride, registration begins at 9 a.m. and will continue through 10:30 a.m. at Vandervest Harley-Davidson in Green Bay. The post-ride party begins at 3 p.m. at Lambeau Field in the North Loft, which can be accessed through the Bellin Health Gate. The party will include food and drink for purchase, a silent and live auction and fun while bringing awareness to cancer. Attendees will also have the opportunity to get autographs from Packers players in exchange for a $10 donation to the event.
  • Tue., Jun. 11, 2013 11:30AM - 1:00PM CDT Organized Team Activities (OTAs) The Packers announced details on the remainder of their offseason schedule, including the fact that five of the team’s offseason practices will be open to the public, weather permitting.

    The open practices will be three organized team activities (OTAs) and two mandatory minicamp workouts. The open OTA practices are slated for three Tuesdays — May 21, May 28 and June 11 — and will begin at 11:30 a.m. CT. The two mandatory minicamp practices are scheduled for June 4 and 5 with a start time TBA.

    Due to ongoing preparations on Ray Nitschke Field for training camp, the OTA and minicamp workouts will be held on Clarke Hinkle Field this year. Viewing of the open practices will be standing-room only along the Oneida Street side of Hinkle Field.

  • Wed., Jul. 24, 2013 11:00AM - 1:00PM CDT Packers Shareholders Meeting

    The Green Bay Packers 2013 Annual Meeting of Shareholders will be held Wednesday, July 24, at 11 a.m., at Lambeau Field. The meeting will take place rain or shine.

News

Print
RSS

Lambeau Field Atrium renovations set to begin this offseason

Posted Jan 8, 2013

Work is final phase of stadium renovation project that began in 2011


The Green Bay Packers will begin renovations to the Lambeau Field Atrium this offseason and will continue work on the project through the next two offseasons, with work scheduled to be fully complete in June of 2015.

Highlights of the project include a new Packers Pro Shop, located in what will be a revamped lower level of the Atrium, new locations for the Packers Hall of Fame and Curly’s Pub, a new east-side entry gate to enhance ingress and egress, and a larger Oneida Nation Gate that includes a plaza area and a more prominent connection to Oneida Street.

Additionally, the players’ parking lot will move to the south side of the Oneida Nation Gate, with access via a tunnel under the enlarged gate. This enhancement will further open up access to the east side of the Atrium, with parking adjacent to the new east side entrance.

“We’re excited to begin work this offseason on the Atrium renovation,” said Packers President/CEO Mark Murphy. “We’re looking forward to providing all our guests an even better experience. The design and new layout will benefit everyone.”

The project, with a cost of $140.5 million, is the final phase of stadium renovation work that began in 2011 and included a new sound system, new video boards, two new gates and approximately 7,000 new seats in the south end zone. Funding for this phase will come from the Packers through private financing ($85.5 million) and a loan from the NFL G4 program ($55 million). In total, including the current project in the south end zone, renovations to the stadium will cost $286.5 million, with no funding coming from public tax money.

During the course of the renovation, the Packers Pro Shop will remain open as it transitions from its current to its new location. The Packers Hall of Fame and Curly’s Pub will close while their new locations are being constructed. The date and duration of closing periods will be determined when more detailed construction plans are established.

In addition to the public areas, the football facilities will receive some upgrades as well, including space for conditioning and team walkthroughs. This aspect of the renovations keeps the team’s football operations up-to-date with the latest technology and best practices.

This phase of the renovation will continue to be an economic impact and benefit to the community. The second phase is expected to employ approximately 1,500 workers over the next two years and provide more than $60 million in wages.

You May Also Be Interested in...

Recent Videos

  • Packers reflect on fun week on road, raising money

    (6:12) Posted 7 hours ago

    The Green Bay Packers Tailgate Tour's eighth year came to a close after a 691-mile trek through Wisconsin and Iowa. See what the traveling party had to say about the tour coming to an end. More than $300,000 was raised collectively for the benefitting charities.

  • Cobb and Bush continue push-up battle on tour

    (3:22) Posted May 18, 2013

    While the players continued demanding push-ups for lost card games, the Tailgate Tour made stops at Challenge Academy and Fennimore High School, before heading to the tailgate party at Tomah Recreation Park.

  • Video Ask Vic: Lightning Round

    (2:58) Posted May 18, 2013

    In this week's 'Video Ask Vic,' packers.com editor Vic Ketchman in the bowl at Lambeau Field with a twist, a lightning round of questions from fans.